Search
Advanced search
Back

Electricity

Notice category:
Energy
Notice type:
Electricity
Publication date:
Edition:
The Edinburgh Gazette
Notice ID:
4913565
Notice code:
2103

ENERGIEKONTOR UK LTD

ELECTRICITY ACT 1989

TOWN AND COUNTRY PLANNING (SCOTLAND) ACT 1997

THE ELECTRICITY WORKS (ENVIRONMENTAL IMPACT ASSESSMENT) (SCOTLAND) REGULATIONS 2017

Notice is hereby given that Energiekontor UK Ltd, company registration number 03830819, with its Registered Office at 114 St Martin’s Lane, London WC2N 4BE has applied to the Scottish Ministers for consent under Section 36 of the Electricity Act 1989 to construct and operate a wind farm known as Coille Linne Wind Farm approximately 21.9km north of Lairg and 16km south-east of Altnaharra (Central Grid Reference: 245144, 924091). The installed capacity of the proposed generating station would be approximately 113MW comprising of up to 15 turbines with a ground to blade tip height of 250 metres. The proposed development is subject to Environmental Impact Assessment (EIA) and an EIA Report has been produced.

The Company has also requested a direction under section 57(2) of the Town and Country Planning (Scotland) Act 1997 that planning permission for the development be deemed to be granted.

A copy of the application, with a plan showing the land to which it relates, together with a copy of the EIA Report discussing the Company’s proposals in more detail and presenting an analysis of the environmental implications, are available for public inspection in person, free of charge, during normal office hours at:

Location Opening hours Address
Lairg Library Mon - 10:00 - 14:00 The Main St
Tue - 12:00 - 15:30; 16:00 - 19:00 Lairg IV27 4DD
Wed - Closed
Thurs - 10:00 - 14:00
Fri - 12:00 - 15:00
Sat - Closed
Sun - Closed

The EIA Report can also be viewed on the application website at https://energiekontor.co.uk/our-projects/coillelinne-wind-farm/ or at www.energyconsents.scot under application reference ECU00005163.

Copies of the EIA Report may be obtained from Energiekontor’ s Project Manager Calum Morris (email: calum.morris@energiekontor.com) at a charge of £1,550.00 hard copy and free of charge on USB. Copies of a short Non-Technical Summary are available free of charge.

Any representations on the application may be submitted by email to the Scottish Government via representations@gov.scot; or by post to the Scottish Government, Energy Consents Unit, 4th Floor, 5 Atlantic Quay, 150 Broomielaw, Glasgow, G2 8LU, identifying the proposal and specifying the grounds for representation.

Written or emailed representations should be dated, clearly stating the name (in block capitals) and full postal address of those making representations.

Emailed representations should also include the full return email address of those making representations.

Only representations sent by email to representations@gov.scot will receive acknowledgement.

All representations should be received not later than Tuesday 5th of August 2025 although the Scottish Ministers may consider representations received after this date.

Any subsequent additional information which is submitted by the developer will be subject to further public notice in this manner, and representations to such information will be accepted as per this notice.

Where the Scottish Ministers are required to, or decide to exercise their discretion to do so, they can cause a public inquiry to be held.

Following examination of the environmental information, the Scottish Ministers will determine the application for consent in one of two ways:

· consent the proposal, with or without conditions attached; or

· reject the proposal

General Data Protection Regulations

The Scottish Government processes representations under the Electricity Act 1989. To support transparency in decision making, the Scottish Government publishes online at www.energyconsents.scot.

A privacy notice is published on the Help page at www.energyconsents.scot. This explains how the Scottish Government processes your personal information. If you have any concerns about the processing of your personal information by the Scottish Government, please email EconsentsAdmin@gov.scot or write to Scottish Government, Energy Consents Unit, 4th Floor, 5 Atlantic Quay, 150 Broomielaw, Glasgow, G2 8LU.